Striping and Asphalt Projects Underway this Month

June 18, 2014 -- CNM will have a number of parking lot striping projects and one asphalt project underway this month with the goal of completing them before June 30. .All the dates and times below are subject to change due to weather conditions. ACE Asphalt will be at most of the job sites by 2:30 a.m.
July 16, 2015

Striping & Repairs Schedule
RRC – Ace Asphalt will begin striping on June 20, starting with the east side of the parking lot and moving toward the west. At 7 a.m. they will block off the area that they have left to work on so that individuals may not park in that area. As they complete the parking lot, they will open the parking areas to accommodate individuals trying to park in that lot.

SVC - Striping will start on June 20 after the RRC has been completed. Ace will start striping again on June 21. and will block off the northern half of the back (East) parking lot. They will complete the striping on the June 21.

WSC – Striping will start on June 24 and go through June 28.

JMMC –Asphalt work will begin on June 25 through June 30. The southern parking lot (South Lot 1) with disabled spaces will be blocked off and opened back on June 30. That lot will be restriped on June 29. The temporary disabled spaces that were striped in that area will be restriped back into regular parking spaces. This will be the only area to be restriped.